Terminal 2 - Boarding Area D - Special Systems Installation, Master Test Plan
| Start Date: February 2012 | Client: T2 Partners |
| End Date: July 2009 | Type of Work: Consulting & Documentation Development |
| Ongoing Support: No |
Project Summary:
Based on the successful work of preparing the Design Narrative for the Terminal 2 Boarding Area D Renovation Project, Barich, Inc. was contracted in July of 2009 to develop the Master Test Plan (MTP). The renovation project required a complex testing process for the special systems infrastructure, software, and hardware to achieve maximum functionality, incur minimal problems at commissioning, and to support on-going business of the airport terminal. The MTP ensures all test specifications are managed and reported for all of the Special Systems implemented in the Terminal 2 renovation project. Barich, Inc. with significant experience and knowledge of airport operational systems and installations, provided the resources to deliver a comprehensive and concise test management program.
The Master Test Plan included:
- Test strategy for structuring all levels of testing
- System and sub system dependencies
- Test planning requirements and deliverables
- Test execution requirements and deliverables
- Execution and progress monitoring approach for the test program
- Process flows for test plan approvals, test execution communication, and problem resolution
Project Status:
The project was completed and the Master Test Plan signed off in July 2009. Following this work, Barich, Inc. was retained for the Master Test Plan Execution phase of the Terminal 2 - Boarding Area D renovation project.